This project involves repairing the NMS TR4B transformer following a fault, and improving the safety of transformers at the CTE2 power plant by supplying and installing terminal covers. The aim is to restore safe operation in compliance with electrical protection requirements.
- nms tr4b transformer repair service.
- Supply and installation of terminal covers for cte2 transformers.
Challenges
- Unexpected failure affecting TR4B transformer availability.
- Compatibility constraints for terminal cover installation.
- Securing the site during partial power operation.
Solutions
- Rapid diagnosis and targeted replacement of defective internal components.
- Custom-built according to the technical specifications of existing equipment.
- Installation of beaconing and reinforced PPE procedures.