Diagnosis and Optimization of Source Substation Grounding Circuits
- Projects
- Redal

Category:
Services and Expertise
Client:
Redal
Date:
August 2024
Project details
The aim of this project is to assess and optimize the earthing circuits at the 60/20 kV source substations at Agdal Tabriquet, Riad and Ameur, as well as the 225/20 kV source substation at Riad. Through an in-depth diagnosis, the aim is to identify any non-conformities, enhance operational safety and guarantee compliance with current standards for the protection of people and equipment.
- Diagnosis of grounding circuits at 60/20 KV AGDAL TABRIQUET, RIAD & AMEUR substations
- Diagnosis of earthing circuits on 225/20KV RIAD source substations
Challenges
- Limited access to facilities during peak network hours.
- Incomplete initial technical data for some older workstations.
- Heterogeneity of existing grounding systems.
Solutions
- Nightly planning of interventions in coordination with operating teams.
- On-site collection and cross-referencing with available physical archives.
- Comparative analysis and adaptation of the diagnostic methods used.